Construction Updates and Detours

  1. Sand Bag Filling Station

    In advance of the predicted weather event this week, the City of Seaside has set up a sand bag filling station for residents at the Seaside Fire Station. Read on...
  2. CONSTRUCTION NOTICE - Drainage Inlet Improvement Project

    Monterey Peninsula Engineering will start construction of the FY 2023/2024 Drainage Inlet Improvement Project on November 27, 2023, for the City of Seaside. Read on...
  1. Construction Notice: Highland Otis Park Playground Replacement

    Kraemer Engineering Incorporated will start the construction of the Highland Otis Park Playground Replacement Project for the City of Seaside on September 25, 2023. Read on...
  1. CONSTRUCTION NOTICE: Fernando Park Improvements

    Kraemer Engineering Inc. will start the construction of the Fernando Park Improvements Project for the City of Seaside on September 13, 2023. Read on...
View All News
  1. City Projects In Construction
  2. City Projects in Design
  3. City Projects out to BiD
  4. City Planned Projects
  5.  Outside Agency Projects
  6. Seaside County Sanitation District Projects
  7. Development Projects

Drainage Inlet Improvement Project

1600 Block of San Pablo Avenue

Monterey Peninsula Engineering will start construction of the FY 2023/2024 Drainage Inlet Improvement Project on November 27, 2023, for the City of Seaside. The project is scheduled to continue through January of 2024.

 The Project construction includes the construction of new storm drain line, a new storm drain catch basin, and roadway paving. All work is scheduled to take place in the 1600 block of San Pablo Avenue.

 During the construction, traffic and pedestrian control may be in place for public safety. Parking may be restricted at select locations, and lane closures may be required; motorists should expect delays. 

 For more information, contact Patrick Grogan, with the City of Seaside Public Works Department, at (831) 899-6885, or by email at pgrogan@ci.seaside.ca.us

WE APOLOGIZE FOR ANY INCONVENIENCE AND APPRECIATE YOUR PATIENCE DURING THIS TIME.

_______________________________________________________________________________________________________________________________________________________________________________________


2023 Hot Spot Pavement Repairs

Citywide

CONSTRUCTION UPDATED as of October 13, 2023

Don Chapin Company Inc. started the construction of the 2023 Hot Spot Pavement Repair Project for the City of Seaside on September 25, 2023.

Project Scope:  Construction includes localized pavement base repairs throughout the City, thin pavement overlays, striping, and utility adjustments.

Construction Status:  Digouts and thin pavement overlays have been COMPLETED on the following roadways:  Circle Ave., Metz Ave., Waring St., East Frontage Road, Baker St., Ord Grove Ave., Darwin St., Elm Ave., and Amador Ave.

The Contractor will remobilize to complete the remaining roadways STARTING OCTOBER 16, 2023 (see yellow highlight, below):  Roberts Ave., Alta Vista Ct., Luxton St., Sonoma Ave., Trinity Ave.

Striping and utility adjustments will be performed the week of October 23, 2023.

Safety:  During the construction, traffic and pedestrian control may be in place for public safety. Parking may be restricted at select locations.  Road and lane closures may be required; detours will be in place if necessary and motorists should expect delays. 

Contact:  For more information, contact Leslie Llantero, with the City of Seaside Public Works Department, at (831) 899-6832, or by email at lllantero@ci.seaside.ca.us 

Hot Spot Public Notice Update

WE APOLOGIZE FOR ANY INCONVENIENCE AND APPRECIATE YOUR PATIENCE DURING THIS TIME.

_______________________________________________________________________________________________________________________________________________________________________________________

Fernando Park Improvements

Between Mingo Avenue and San Pablo Avenue

Kraemer Engineering Inc. will start the construction of the Fernando Park Improvements Project for the City of Seaside on September 13, 2023.

The Project construction will include earthwork and grading, and installation of play equipment, an accessible picnic table with bench, hand sanitation station, wood chip play surfacing, an accessible ramp, rock wall, concrete curbs, and a concrete walkway. The Project is expected to be complete by the end of December 2023.

During the construction, traffic and pedestrian control may be in place for public safety. Parking may be restricted at select locations. 

For more information, contact Nisha Patel, with the City of Seaside Public Works Department, at (831) 899-6884, or by email at npatel@ci.seaside.ca.us

WE APOLOGIZE FOR ANY INCONVENIENCE AND APPRECIATE YOUR PATIENCE DURING THIS TIME.

_______________________________________________________________________________________________________________________________________________________________________________________

City Hall and Library Parking Lot Repaving

440 Harcourt Ave

UPDATED AUGUST 15, 2023

Monterey Peninsula Engineering will start construction of the FY 2023/2024 City Hall and Library Parking Lot Repave Project on August 21, 2023 for the City of Seaside. The project is scheduled to continue through October of 2023.

Minor utility location work will take place on August 16, 2023, in preparation for the start of the project.

The Project construction includes the construction of new sanitary sewer line, ADA improvements, and sidewalk, parking lot, and roadway paving. All work is scheduled to take place in the City Hall parking lot, the 500 block of Harcourt Avenue, and the 1200 block of Sutter Street.

During the construction, traffic and pedestrian control may be in place for public safety. Parking may be restricted at select locations, and lane closures may be required; motorists should expect delays. 

Parking will be available on Harcourt Avenue, Sutter Street, and in the parking lot behind the library from August 21 to September 20. Parking will be available on Harcourt Avenue, and in the parking lot in front of City Hall from September 25 until project completion.

For more information, or for ADA accommodations, contact Patrick Grogan, with the City of Seaside Public Works Department, at (831) 899-6885, or by email at pgrogan@ci.seaside.ca.us.

city hall parking

WE APOLOGIZE FOR ANY INCONVENIENCE AND APPRECIATE YOUR PATIENCE DURING THIS TIME.

_______________________________________________________________________________________________________________________________________________________________________________________

Ord Terrace Elementary School Crossing Improvements

La Salle Avenue at Lindberg Court

Coastal Paving and Excavating Incorporated will start the construction of the Ord Terrace Elementary School Crossing Improvements Project for the City of Seaside at the end of June 2023.

Project construction includes constructing a curb extension, accessible curb ramps and median refuge island for an offset lighted crosswalk on La Salle Avenue at Lindberg Court, installing flexible delineators, striping and associated signage. The Project is expected to be complete by the end of July 2023.

During the construction, traffic and pedestrian control may be in place for public safety. Parking may be restricted at select locations, and lane closures may be required; motorists should expect delays. 

For more information, contact Leslie Llantero, with the City of Seaside Public Works Department, at (831) 899-6832, or by email at lllantero@ci.seaside.ca.us 

Capture

WE APOLOGIZE FOR ANY INCONVENIENCE AND APPRECIATE YOUR PATIENCE DURING THIS TIME.

_______________________________________________________________________________________________________________________________________________________________________________________

Lincoln Cunningham Park Basketball Court Improvements Project

North of San Pablo Avenue, between Yosemite Street and Lincoln Street

Monterey Peninsula Engineering will start the construction of the Lincoln Cunningham Park Basketball Court Improvements Project for the City of Seaside at the end of June 2023.

Project construction includes demolition and earthwork; storm drain pipes, structure, and bioretention pond; concrete curbs, concrete pad and asphalt paving, site retaining walls; hot mix asphalt paving; site furnishings including basketball hoops, posts, and benches; and planting (seeding) and maintenance during plant establishment period. The Project is expected to be complete by the end of October 2023.

During construction, traffic and pedestrian control may be in place for public safety. Parking may be restricted at select locations. 

For more information, contact Anthony Lehman, with Wallace Group, at (805) 544-4011, or by email at  AnthonyL@wallacegroup.us 

WE APOLOGIZE FOR ANY INCONVENIENCE AND APPRECIATE YOUR PATIENCE DURING THIS TIME.

_______________________________________________________________________________________________________________________________________________________________________________________

Cutino Park Improvements - Part 2, Phase 1

San Pablo Avenue and Noche Buena Street

Updated October 11, 2023

Granite Rock Company will begin construction on the Cutino Park Improvement project, Part 2, Phase 1 for the City of Seaside on April 13, 2023.  The construction is expected to be complete by the end of November 2023.

The Project construction includes demolition of existing concrete structures; removal of trees; installation of new lawn and irrigation, picnic tables and benches, and visitor bleachers and concrete pad; and construction of ADA-compliant pathways, a new parking lot with lighting, and playground with new equipment.

Preconstruction activities include installation of site fencing, temporary erosion control devices, demolition of existing concrete structures, and removal of trees.

Nearby residents should expect typical construction noise. If you have any questions about the construction work, please contact Kirstin van Gend at (831) 899-6838

WE APOLOGIZE FOR ANY INCONVENIENCE AND APPRECIATE YOUR PATIENCE DURING THIS TIME.

_______________________________________________________________________________________________________________________________________________________________________________________

FY 2021/2022 Pavement Rehabilitation

Kimball Avenue from Fremont Boulevard to Wheeler Street and Wheeler Street from Kimball Avenue to Hilby Avenue

Granite Rock Company started construction of the FY 2021/2022 Pavement Rehabilitation Project for the City of Seaside on October 24, 2022.  

The Project construction includes pavement rehabilitation on Kimball Avenue from Fremont Boulevard to Wheeler Street and Wheeler Street from Hilby Avenue to Kimball Avenue, base repairs and microsurfacing of the northern and southern ends of Fremont Boulevard, several base repair locations throughout the City, and citywide street restriping.

4.5.23 UPDATE - Kimball & Wheeler Striping

Striping activities on Kimball Avenue and Wheeler Street is scheduled to begin on April 10, 2023 and will last for 3 days.  On-street parking will be restricted during the striping activities on Kimball Avenue.  Adhere to the “No Parking” signs.  

Fremont Slurry Sealing

Crack filling will begin on Fremont Boulevard the week of April 17, 2023.  Slurry seal will start the following week on April 24, 2023 and is scheduled to take 2 days. Striping of Fremont Boulevard is scheduled for the first week of May.  Detours will be in place, motorist should expect delays, and alternative routes are recommended.

Citywide Street Restriping

Citywide street restriping will begin the on April 13, 2023 and expected to last several weeks.  Contractor will begin with centerline restriping.  Localized traffic control will be in place.

If you have any questions about the construction work, please contact Leslie Llantero, Assistant Engineer at (831) 899-6832.

WE APOLOGIZE FOR ANY INCONVENIENCE AND APPRECIATE YOUR PATIENCE DURING THIS TIME.

____________________________________________________________________________________________________________________________________________________________________________________

Fort Ord Military Reservation Property Deconstruction and Demolition Phase 1A Project

Randazzo Enterprises, Inc. started construction of the Fort Ord Military Reservation Property Deconstruction and Demolition Phase 1A Project for the City of Seaside on June 13, 2022.  

The Project scope includes demolition and removal of the visitor center building, pavement, select hardscape, select landscaping, removal of onsite utilities, and excavation & disposal of onsite soil at the property on the corner of Lightfighter Drive and 2nd Avenue. 

The work was started mid- June then placed on hold as Randazzo waited on guidance regarding additional soil excavation within the existing project footprint.

Subsequent soil excavation and disposal activities are anticipated to continue on December 14, 2022, and are expected to be complete by mid-January, 2023. Following completion of the remaining soil excavation, Randazzo will work through minor remaining work to finalize the project and demobilize from the site. 

Impact on surrounding areas, including traffic on Lightfighter Drive is anticipated to be minor. However, there may be intermittent interruptions on ingress and egress of Lightfighter Drive to 2nd Avenue as heavy equipment and hauling trucks enter and leave the subject property. Lane closures are not anticipated, though traffic and pedestrian control may be in place adjacent to the work for public safety. 

If you have any questions about the construction work, please contact the City of Seaside Public Works and Engineering Department at (831) 899-6835, or Randazzo Enterprises, Inc. at (831) 633-4420.

WE APOLOGIZE FOR ANY INCONVENIENCE AND APPRECIATE YOUR PATIENCE DURING THIS TIME.

_______________________________________________________________________________________________________________________________________________________________________________________

Del Monte Manor Storm Drain Improvements (H.E.M Plaza)

1442 Yosemite Street

Monterey Peninsula Engineering started construction of the FY 2021/2022 Del Monte Manor Storm Drain Improvements Project on June 21, 2022 for the City of Seaside. The project is scheduled to continue through February of 2023.

The Project construction includes the construction of a storm water infiltrator, regrading of the storm water retention basin, storm drain improvements in Yosemite Street and Sonoma Avenue, construction of an irrigation system, fencing, landscaping, and sidewalk and roadway paving. All work scheduled to take place in the 1400 block of Yosemite Street and the 1600 block of Sonoma Avenue has been completed. Remaining work involves powering the irrigation system, and installing flow monitoring equipment within the project boundary. 

Traffic delays, roadway closures, or sidewalk closures resulting from this work are not anticipated. Brief power interruptions may occur during the power connection of the irrigation system, which is expected to take place in February 2023. If you have any questions about the construction work, please contact Patrick Grogan at (831) 899-6885.

DMM Photo


_______________________________________________________________________________________________________________________________________________________________________________________