[ARCHIVED] CONSTRUCTION NOTICE - Pavement Rehab

CONSTRUCTION NOTICE 

April 5, 2023

Granite Rock Company started construction of the FY 2021/2022 Pavement Rehabilitation Project for the City of Seaside on October 24, 2022.  

The Project construction includes pavement rehabilitation on Kimball Avenue from Fremont Boulevard to Wheeler Street and Wheeler Street from Hilby Avenue to Kimball Avenue, base repairs and slurry sealing of the northern and southern ends of Fremont Boulevard, several base repair locations throughout the City, and citywide street restriping.

UPDATE – Kimball & Wheeler Striping

Striping activities on Kimball Avenue and Wheeler Street is scheduled to begin on April 10, 2023 and will last for 3 days.  On-street parking will be restricted during the striping activities on Kimball Avenue.  Adhere to the “No Parking” signs.  

Fremont Slurry Sealing

Crack filling will begin on Fremont Boulevard the week of April 17, 2023.  Slurry seal will start the following week on April 24, 2023 and is scheduled to take 2 days. Striping of Fremont Boulevard is scheduled for the first week of May.  Detours will be in place, motorist should expect delays, and alternative routes are recommended.

Citywide Street Restriping

Citywide street restriping will begin the on April 13, 2023 and expected to last several weeks.  Contractor will begin with centerline restriping.  Localized traffic control will be in place.

If you have any questions about the construction work, please contact Leslie Llantero, Assistant Engineer at (831) 899-6832.

WE APOLOGIZE FOR ANY INCONVENIENCE AND APPRECIATE YOUR PATIENCE DURING THIS TIME