Posted on: July 17, 2017

[ARCHIVED] West Broadway Urban Village Infrastructure Update

West Broadway Construction

WBUVBroadway Avenue is getting over $7 million in street improvements. This will result in wider sidewalks, new bicycle lanes, bulb-outs for safer pedestrian crossing, a signal light at Alhambra, and one less traffic lane in each direction. Broadway on-street parking will remain available. Traffic is expected to flow smoother due to the signal light. Construction began with tree work in January 2017 and completion is anticipated late Spring 2018.


CONSTRUCTION SCHEDULE

The project started at the Fremont end of Broadway, moving towards Del Monte. Broadway is now a one-way street (temporarily) through the end of the project. Traffic will move from Fremont West toward Del Monte during the current phase of construction. This allows for parking on one lane Please be patient during the project and drive carefully. Construction is expected to be complete late Spring 2018.


COMPLETED Week of November 20.

MPE prepared subgrade for curb and gutter, and made the project site storm ready for rain forecasted over the holiday weekend.  Aparicio Concrete poured curb and gutter at the Alhambra Street intersection at the west side of the Calaveras Street intersection. The remainder of the week, Aparicio completed curb & gutter forms east the City Center access road. Darrel Varni Electric (DVE) excavated and poured streetlight foundations east of Calaveras Street.  For public traffic, Calaveras Street access remained open, and Alhambra St was re-opened to public traffic before Thanksgiving.



Next Week’s Schedule (week of November 27): 

Aparicio Concrete will pour curb and gutter at the east intersection at Calaveras Street, and then begin sidewalk concrete pouring at the west end of the project near Hillsdale Street.  DVE will be onsite to begin work on the utility cabinets and poles for the Alhambra traffic signals. The Alhambra Street access will remain open to public traffic.

                                                                     


ABOUT THE CONSTRUCTION TEAM


Monterey Peninsula Engineering (MPE) was awarded the construction contract on March 2, 2017 to construct the West Broadway Urban Village Infrastructure Improvements Project.  MNS Engineers (MNS) was retained to perform construction management services for the City overseeing the contractor’s daily operations and management of the project.  MNS staff includes a survey crew, resident engineer, construction inspector, material testing, and environmental biologist.  MNS employs a full time construction inspector for the project who is onsite daily.  Surveying crew and material testing is provided as needed. 


PROGRESS UPDATES

To receive TEXT updates, send a text message to 888777 with the message BROADWAY.  This page will follow the progress of the infrastructure improvements as they happen. Check back regularly to find out how work is proceeding. Or Follow us on Twitter @City_of_Seaside or www.Facebook.com/SeasideCAUnder Construction Icon

 