Group 1
Includes the Seaside and Parker Flats MRAs. Munitions responses (removal) have been completed for both MRAs in accordance with the intended reuses. Among the proposed reuses for this group are residential and non-residential development with borderland interface and habitat reserve.
For a much more detailed description of both MRAs, the cleanup, proposed reuses and land use controls, see the Proposed Plan, the Parker Flats (Phase II) MRA Record of Decision, the Parker Flats (Phase I) MRA Record of Decision, and Land Use Control Implementation Plan / Operation & Maintenance Plan for Group 1.
Group 1 Land Use Control | Parker Flats MRA (Phase I) | Parker Flats MRA (Phase II) | Seaside |
---|---|---|---|
Munitions recognition training for people involved in ground-disturbing activities | ✓ | ✓ | |
Construction support for ground-disturbing or intrusive activities | ✓ | ✓ | |
Access management measures for habitat reserve | ✓ | ||
Restrictions in residential use | ✓ | ✓ | |
Restrictions prohibiting inconsistent uses | ✓ |
Group 2
Includes the CSUMB Off-Campus MRA and the County North MRA. While removal action was not required in the County North MRA, the Munitions response (removal) has been completed for the CSUMB Off-Campus MRA in accordance with the intended reuses. Among the proposed reuses for the CSUMB Off-Campus MRA are future CSUMB campus uses.
For a much more detailed description of this group, the cleanup, proposed reuses and land use controls, see the Proposed Plan, the CSUMB Off-Campus MRA Record of Decision and the Land Use Control Implementation Plan / Operation & Maintenance Plan for Group 2. No further action regarding munitions response is required for the County North MRA.
Group 2 Land Use Control | County North | CSUMB Off-Campus |
---|---|---|
Munitions recognition training for people involved in ground-disturbing activities | N/A | ✓ |
Construction support for ground-disturbing or intrusive activities | N/A | ✓ |
Access management measures for habitat reserve | N/A | |
Restrictions in residential use | N/A | ✓ |
Restrictions prohibiting inconsistent uses | N/A |
Group 3
Includes the Del Rey Oaks (DRO)/Monterey, Laguna Seca Parking and Military Operations on Urban Terrain (MOUT) MRAs. Munitions responses (removal) have been completed for all areas in accordance with the intended reuses. The DRO/Monterey MRA includes three proposed reuses: habitat management, non-residential development, and South Boundary Road right-of-way. The Laguna Seca Parking MRA as proposed for reuse as open space and area for overflow parking. Finally, the MOUT MRA will be used to provide training by Monterey Peninsula College.
For a much more detailed description, see the Proposed Plan, the MOUT Site MRA Record of Decision and Land Use Control Implementation Plan / Operation & Maintenance Plan for Group 3.
Group 3 Land Use Control | DRO/Monterey | Laguna Seca Parking | MOUT |
---|---|---|---|
Munitions recognition training for people involved in ground-disturbing activities | ✓ | ✓ | ✓ |
Construction support for ground-disturbing or intrusive activities | ✓ | ✓ | ✓ |
Access management measures for habitat reserve | |||
Restrictions in residential use | ✓ | ✓ | ✓ |
Restrictions prohibiting inconsistent uses |
Group 4
Includes the Future East Garrison MRA. Munitions responses (removal) have been completed for this areas in accordance with the intended reuses. Among the proposed reuses are residential and non-residential development with borderland interface and habitat reserve.
For a much more detailed description of this group, the cleanup, proposed reuses and land use controls, see the Proposed Plan, the Future East Garrison MRA Record of Decision and Land Use Control Implementation Plan / Operation & Maintenance Plan for Group 4.
Group 4 Land Use Control | Future East Garrison |
---|---|
Munitions recognition training for people involved in ground-disturbing activities | ✓ |
Construction support for ground-disturbing or intrusive activities | ✓ |
Access management measures for habitat reserve | ✓ |
Restrictions in residential use | ✓ |
Restrictions prohibiting inconsistent uses | ✓ |
Interim Action Ranges
Includes the Interim Action Ranges MRA. Munitions responses (removal) have been completed for this areas in accordance with the intended reuses. Among the proposed reuses include non-residential development with borderland interface and habitat reserve
For a much more detailed description of this group, the cleanup, proposed reuses and land use controls, see the Proposed Plan, Record of Decision and Land Use Control Implementation Plan / Operation & Maintenance Plan for Interim Action Ranges MRA.
Land Use Control | Interim Action Ranges |
---|---|
Munitions recognition training for people involved in ground-disturbing activities | ✓ |
Construction support for ground-disturbing or intrusive activities | ✓ |
Access management measures for habitat reserve | |
Restrictions in residential use | ✓ |
Restrictions prohibiting inconsistent uses | ✓ |